The bill improves long-term planning for America’s electric grid, helping reduce costly outages, strengthen reliability during extreme weather, and keep electricity affordable for families in Sacramento and communities across the country.
Improve long-term planning for America's electric grid to reduce costly outages, strengthen reliability during extreme weather, and keep electricity affordable.
Occurrences
Evidence
FERC issued tailored show-cause orders to all six regional grid operators, directing them to justify or reform rules for connecting data centers, manufacturing facilities, and other large loads; FERC said the action aims to ensure reliable, affordable power while protecting ratepayers, with 60-day tariff responses and 30-day generation-adequacy reports.
FERC staff described Order No. 1920 as requiring transmission providers to conduct long-term, forward-looking regional transmission planning; plan ahead at least 20 years; update planning at least every five years; and evaluate reliability and economic benefits including mitigation of extreme weather events and unexpected system conditions.
FERC said Order No. 1920-A largely sustained Order No. 1920's requirement for Long-Term Regional Transmission Planning, while clarifying requirements and strengthening state involvement in scenario development and cost allocation.
FERC staff said the Infrastructure Investment and Jobs Act amended Federal Power Act section 216 to clarify that FERC may issue permits for electric transmission facilities in National Corridors if a state has denied a siting application; the final rule updated FERC's transmission-siting permit regulations.
The House Clerk records Roll Call 369 on H.R. 3684, the INVEST in America Act / Infrastructure Investment and Jobs Act, as passed 228-206 on Nov. 5, 2021; Rep. Doris Matsui is recorded as voting Yea.
GovInfo records Public Law 117-58, the Infrastructure Investment and Jobs Act, enacted Nov. 15, 2021. The law includes federal energy infrastructure provisions, including grid infrastructure and resiliency programs and transmission-related authorities.
Assessments
The core promise was to improve long-term electric-grid planning for reliability, extreme weather resilience, and affordability. During Matsui's current federal tenure, FERC Order No. 1920 created a binding long-term regional transmission planning framework requiring at least 20-year planning, periodic updates, and evaluation of reliability, economic, extreme-weather, and customer-cost benefits; Order No. 1920-A sustained that framework. Matsui also voted for the enacted Infrastructure Investment and Jobs Act, which supported grid resilience and transmission authorities. The evidence does not prove completed outage reductions or lower bills, but the promised planning reform itself was substantially delivered in the same term.