This report makes clear that the federal government has broken its promise to Puerto Rico, and Committee Democrats are going to keep demanding accountability until that changes.
Huffman will keep demanding accountability until the federal government delivers on Puerto Rico grid recovery and modernization funding.
Occurrences
Evidence
AP reported that an 86-page GAO audit released by U.S. Democratic lawmakers found only 25% of roughly $14 billion obligated for Puerto Rico's power grid had reached the territory. AP attributed a statement to California Democratic Rep. Jared Huffman/Hoffman saying Puerto Rico had waited nine years while appropriated billions mostly had not arrived. The same report said GAO recommended FEMA guidance updates and DOE coordination steps.
AP reported that U.S. Democratic lawmakers visited Puerto Rico and pledged corrective actions after mayors raised delayed reimbursements and project approvals. It reported nearly $43 billion allocated, nearly $40 billion obligated, and $12.7 billion disbursed, with about 30% of projects still pending and FEMA workforce reductions slowing recovery work.
AP reported that DOE canceled three Puerto Rico solar and battery programs, including one worth $400 million, and planned to reallocate up to $350 million from distributed solar systems to power-generation fixes, while it was not immediately clear whether that funding had been allocated. The article said the projects came from a $1 billion congressional fund for Puerto Rico energy resilience.
Puerto Rico Energy Bureau testimony to the House Natural Resources Committee described June 2024 outages, persistent rolling blackouts, federal funding utilization challenges, and PREPA bankruptcy complications. It said LUMA reported $18.1 million obligated by FEMA for one San Juan vegetation-management project out of 31 island-wide vegetation projects estimated at $1.2 billion, and that the system remained far from the desired remediated condition.
AP reported on a GAO audit finding Puerto Rico had spent less than 10% of more than $23 billion in available federal recovery funds, with more than $11 billion requiring FEMA approval before use. It also reported chronic power outages and that some applications by Puerto Rico's power company and other agencies were expected by 2030 or later.
Assessments
Huffman was tied to a concrete federal oversight and accountability action, including the GAO audit release and public pressure over delayed Puerto Rico grid recovery funds. However, the evidence shows the promised underlying result was not delivered: only a minority of obligated grid funding had reached Puerto Rico, outages and modernization barriers persisted, and some energy resilience programs were canceled or redirected. Because he materially continued demanding accountability but the federal government had not delivered the grid recovery and modernization funding outcome, this is partial rather than delivered.