We will continue to do all we can to support the construction of a stronger and safer bridge over the Patapsco.
Continue supporting the construction of a stronger and safer Francis Scott Key Bridge over the Patapsco.
Occurrences
Evidence
The MDTA newsroom says the agency is carrying out essential design and construction activities for the Francis Scott Key Bridge rebuild. Its latest update says MDTA hosted an in-person industry forum on June 18, 2026 focused on the upcoming procurement for the main span and marine approaches, and the site lists spring 2026 work including offsite material fabrication, permanent pile installation, and trestle construction.
The enacted law provided $8.086 billion for FHWA Emergency Relief and made the federal share 100% for responding to Dali damage to the Francis Scott Key Bridge, including reconstruction of the bridge and approaches.
The House Clerk records H.R. 10545 as passed, 366-34, and lists Rep. Ivey, Democrat of Maryland, voting Yea.
Congress.gov summarizes H.R. 7961 as allowing 100% federal cost-share for emergency relief funds responding to Dali damage to the Francis Scott Key Bridge, including reconstruction.
MDTA's design page says the rebuilt bridge will meet Interstate standards, use a longer cable-stayed main span, provide 230 feet of clearance, and include modern pier protection structures.
The project construction page reports permanent foundation pile installation, temporary trestle construction, completed land demolition, and a test pile program completed in February 2026.
MDTA said it was working with FHWA to advance the rebuild, estimated cost at $4.3-$5.2 billion, and anticipated opening to traffic in late 2030.
The project newsroom listed June 2026 industry forum activity, May 2026 announcements of four construction procurements, and an April 2026 contractor off-ramp notice.
AP reported that Maryland's congressional delegation planned legislation to make clear the federal government would fully cover rebuilding the collapsed Francis Scott Key Bridge.
Assessments
The Francis Scott Key Bridge rebuild is actively moving forward, so the underlying construction-support objective is being realized during Ivey's current term. But the evidence only shows state rebuild activity and ongoing procurement/construction, not that Ivey personally wrote, sponsored, or materially advanced the project enough to claim full credit, so this is partial rather than fully delivered.